Glossary AZ - Content » Title

Published:

A Work Permit is a guarantee of isolation for specific work on specific apparatus.

Published:

The Issuing Authority shall record the first permit transfer in the Transfer section of the permit, and any additional permit transfers on this form. 

Published:

A Work & Test Permit is a guarantee of de-energization when issued under which specific work and tests are done on specific apparatus.

Published:

A Hold-Off Permit is a guarantee of non-reclose for work on or near dynamically alive apparatus.

Published:

Switching Plans shall be used in conjunction with Work Protection permits to ensure worker safety, equipment safety, and system security.

A Switching Plan shall be in place for every permit. 

All locks and tags shall be documented on the Switching Plan.

Published:

If surrender of a permit is required and the Permit Holder is not available, the permit may be surrendered by a WPC Manager.  The designated manager shall:

  • Make a minimum of two attempts to contact the Permit Holder;
  • Obtain signature approval from the Director;
  • Confirm that all workers are clear of the permit zone;
  • Confirm that all apparatus is in a safe condition;
  • Inform the Permit Holder at the earliest opportunity that the permit has been surrendered; and
  • Complete the Permit Holder Notification section of the form.
Published:

May be used to remove a work proection lock if the key is not available, or if the Lock Holder cannot be reached or cannot travel to the work site.

Published:

Joint Use Asset Transfer Form